Elysian Construction Progress and Legal Status 2026: Topped Out, Guaranteed, Licensed

Posted by Khoi Pham on September 5, 2026
0 Comments

Elysian by Gamuda Land seen from above, Lo Lu, Thu Duc

All four Elysian towers topped out by February 2026, fit-out and façade works have reached level 17, and the project carries bank guarantees from Vietcombank and Public Bank. For an off-plan purchase, those are the two things that matter most: real progress and a complete legal file. This article sets out both, plus what a buyer should insist on seeing before signing.

Contents

All four towers topped out in February 2026

The single most important structural milestone is done. The four towers topped out on this schedule:

TowerTopping-out date
Towers A and C5 November 2025
Tower B15 December 2025
Tower D30 January 2026

Topping out matters practically for a buyer. From this point the largest risk in an off-plan purchase — structural works stalling — has passed. What remains is fit-out, façade and landscaping: slow work, but rarely the reason a project halts outright.

All four Elysian towers topped out by February 2026

Progress as at July 2026: fit-out has reached level 17

ItemJune 2026July 2026
StructureTopped out since February 2026Topped out since February 2026
Apartment fit-outUp to level 15Up to level 17
FaçadeUp to level 15Up to level 17
PodiumUnder constructionInterior fit-out of communal amenities
LandscapingInfrastructure worksInfrastructure and landscape packages accelerating

The month-on-month delta tells you the run rate: fit-out and façade are climbing at roughly two floors per month. That is a more useful number for estimating handover than the date printed on the contract.

Fit-out works under way at Elysian

What the Elysian legal file contains

This is the section most buyers skip and the one that determines how safe the transaction actually is. The developer’s file covers:

CategoryDocuments
Land use rightsLand use right certificate issued to the project company, plus land allocation decisions
PlanningApproval of the adjusted 1/500 detailed plan
InvestmentInvestment registration certificate with subsequent amendments; feasibility study appraisal
ConstructionConstruction permit; commencement notice; acceptance records for basement and substructure
Fire safetyFire prevention and fighting design appraisal certificate
SalesLicence to sell future housing; approval of the registered template sale contract
Bank guaranteeGuarantee undertakings from Vietcombank and Public Bank
What the bank guarantee does, and what to ask for
Vietnamese law requires a developer selling future housing to hold a commercial bank guarantee. If the developer fails to hand over as promised, the bank refunds what the buyer has paid. It is the single most important financial protection in an off-plan purchase — and buyers are entitled to receive a guarantee letter issued for their own unit, not just the project-level undertaking. Ask for it in writing.

Three things to confirm before signing

  • The guarantee letter for your specific unit code. The project-level undertaking and the unit-level letter are two different documents.
  • The management fee agreement. Elysian has a separate agreement covering preferential management fees, executed as its own document set alongside the sale contract. Check it is included in what you receive.
  • The email address registered on your contract. The developer issues payment notices and accepts confirmations only through the registered email. Confirmations from any other address are treated as invalid.
Running costs to budget for
Where a unit comes with a named car parking bay, owners generally pay two monthly charges — parking and management. The bay is tied to the apartment: it can be sub-let but not sold separately. Apartments are also fitted with a sprinkler head above the main entrance door.

Frequently asked questions

Has Elysian topped out?
Yes. Towers A and C topped out on 5 November 2025, Tower B on 15 December 2025 and Tower D on 30 January 2026. All four towers were structurally complete by February 2026.
What is the current construction progress at Elysian?
As at July 2026, apartment fit-out and façade works had reached level 17, the podium was in interior fit-out for communal amenities, and the swimming pool structure was complete with surface finishing under way.
Does Elysian have a bank guarantee?
Yes — guarantee undertakings from Vietcombank and Public Bank. Buyers should request the guarantee letter issued for their own unit code, not only the project-level undertaking.
Does Elysian have a licence to sell?
Yes. The file includes the licence to sell future housing, approval of the registered template sale contract, and the fire safety design appraisal certificate.
Can the car parking bay at Elysian be resold?
No. The named parking bay is tied to the apartment. It can be sub-let but cannot be sold separately from the unit it belongs to.
Talk to Realtique about Elysian
Ask us for the current release, price list and payment terms — we answer in English.