Elysian Construction Progress and Legal Status 2026: Topped Out, Guaranteed, Licensed
Elysian by Gamuda Land seen from above, Lo Lu, Thu Duc
All four Elysian towers topped out by February 2026, fit-out and façade works have reached level 17, and the project carries bank guarantees from Vietcombank and Public Bank. For an off-plan purchase, those are the two things that matter most: real progress and a complete legal file. This article sets out both, plus what a buyer should insist on seeing before signing.
Contents
All four towers topped out in February 2026
The single most important structural milestone is done. The four towers topped out on this schedule:
| Tower | Topping-out date |
|---|---|
| Towers A and C | 5 November 2025 |
| Tower B | 15 December 2025 |
| Tower D | 30 January 2026 |
Topping out matters practically for a buyer. From this point the largest risk in an off-plan purchase — structural works stalling — has passed. What remains is fit-out, façade and landscaping: slow work, but rarely the reason a project halts outright.
All four Elysian towers topped out by February 2026
Progress as at July 2026: fit-out has reached level 17
| Item | June 2026 | July 2026 |
|---|---|---|
| Structure | Topped out since February 2026 | Topped out since February 2026 |
| Apartment fit-out | Up to level 15 | Up to level 17 |
| Façade | Up to level 15 | Up to level 17 |
| Podium | Under construction | Interior fit-out of communal amenities |
| Landscaping | Infrastructure works | Infrastructure and landscape packages accelerating |
The month-on-month delta tells you the run rate: fit-out and façade are climbing at roughly two floors per month. That is a more useful number for estimating handover than the date printed on the contract.
Fit-out works under way at Elysian
What the Elysian legal file contains
This is the section most buyers skip and the one that determines how safe the transaction actually is. The developer’s file covers:
| Category | Documents |
|---|---|
| Land use rights | Land use right certificate issued to the project company, plus land allocation decisions |
| Planning | Approval of the adjusted 1/500 detailed plan |
| Investment | Investment registration certificate with subsequent amendments; feasibility study appraisal |
| Construction | Construction permit; commencement notice; acceptance records for basement and substructure |
| Fire safety | Fire prevention and fighting design appraisal certificate |
| Sales | Licence to sell future housing; approval of the registered template sale contract |
| Bank guarantee | Guarantee undertakings from Vietcombank and Public Bank |
Three things to confirm before signing
- The guarantee letter for your specific unit code. The project-level undertaking and the unit-level letter are two different documents.
- The management fee agreement. Elysian has a separate agreement covering preferential management fees, executed as its own document set alongside the sale contract. Check it is included in what you receive.
- The email address registered on your contract. The developer issues payment notices and accepts confirmations only through the registered email. Confirmations from any other address are treated as invalid.
Frequently asked questions