Saigon River Pedestrian Bridge: When Will It Open? Arch Closure Set for 21 October 2026, Linking District 1 With Thu Thiem

Posted by Khoi Pham on October 17, 2026
0 Comments

Update, 3 November 2026: Bach Dang Wharf is set to get two more pedestrian bridges, this time crossing Ton Duc Thang Street — a package worth more than VND 88 billion under a build–transfer contract that asks the city for no payment. Both sit on the District 1 bank and would link Nguyen Hue walking street directly to the riverside park, which is where the 720 m bridge to Thu Thiem lands. See the “Update, 3 November 2026” section below.

Update 24 Oct 2026: Realtique has published a 7-photo story of the 3,400-tonne arch’s journey from Vung Tau to the 21 October closure (Government News Portal photos, credited) — this article remains the milestone tracker.

Updated 22 October 2026 · Short answer: the pedestrian bridge across the Saigon River — linking Bach Dang Wharf park (Saigon ward, former District 1) with the central square and riverside park of Thu Thiem new urban area (An Khanh ward) — closed its arch on the afternoon of 21 October 2026: the 187-metre, 1,400-tonne main span was connected to both piers at about 1 pm and the 2,000-tonne support frame was towed away that evening (VnExpress, 21 October; Tien Phong, 22 October). The arch-and-frame assembly, 3,400 tonnes in total, had been loaded out at Dong Xuyen port on 16 October (Vietnam Government News). Deck, railings, lighting and lifts come next; Nutifood says the bridge is expected to open around Tet 2027, with no formal date yet.

Realtique’s reading of the record: the earlier target of opening around 2 September 2026, reported in May, has slipped, but the project is about 90% complete. Below: the timeline, where the bridge lands and how long it is, the 124 km tow, and what a walkable link to District 1 changes for people living in or buying in Thu Thiem.

Quick Facts

Saigon River Pedestrian Bridge — Updated 3 November 2026

21 Oct 2026
Arch closed — completed afternoon of 21 Oct
3,400 t
Arch + support frame, loaded out 2:15 am, 16 Oct
~720 m
Total length; main arch span 187 m
~VND 1,000bn
Privately funded, sponsored by Nutifood

Table of Contents

Update, 3 November 2026: Two More Footbridges Over Ton Duc Thang Complete the District 1 Walking Network

Ho Chi Minh City’s Department of Construction is circulating a draft contract for a project to build two pedestrian bridges and refurbish wharf bridges B and C at Bach Dang, ahead of negotiations with the investor (VnExpress, 3 Nov 2026).

How it is funded. The investor is Great Wealth Trading and Services Co., Ltd., working under a build–transfer (BT) contract that requires no payment from the city. The company has proposed a budget of more than VND 88 billion from its own and other lawful sources, and will cover construction, management and operation. In return it receives support measures such as the right to install panels and LED screens carrying public messaging alongside commercial advertising, plus amenity service points. Exact locations and specifications remain subject to approval. The city approved the investment policy back in December 2025.

Where they go. One bridge crosses at the Nguyen Hue – Ton Duc Thang junction, in front of the Majestic Saigon Hotel; the other at Thai Van Lung – Ton Duc Thang, in front of The Landmark. Each is a steel structure 6 m wide, fitted with lifts and architectural lighting. The same contract covers refurbishing wharf bridge B (repairs, cleaning, fencing, railings and approach ramps, plus landscaping, power, water, lighting, cameras and greenery along the bank) and turning wharf bridge C into a flower island and green space.

Why this matters for the Thu Thiem crossing. For anyone on foot here, the hard part was never the river — it was Ton Duc Thang Street, a busy traffic artery sitting between Nguyen Hue walking street and the riverside park. These two bridges address exactly that gap. Once built, you could walk from Nguyen Hue over Ton Duc Thang, through the park and onto the 720 m span to Thu Thiem without crossing traffic once. They are the missing link on the District 1 side rather than a standalone amenity.

Timing — read it carefully. The draft puts construction at roughly two months after the site is handed over. But the contract is not signed and no handover date has been announced, so there is no completion date. These bridges were once slated for 30 April this year and slipped while paperwork was finished — which is why “two months” should be read as a build duration, not a promise of an opening day.

Context for buyers and tenants. Nguyen Hue walking street runs 670 m and has drawn thousands of residents and visitors daily since it opened in 2015; Thai Van Lung Street is separately being studied as a model street for urban and traffic civility. Together with the 720 m Thu Thiem bridge that has closed its arch, the west bank is gradually becoming a continuous pedestrian network — the kind of factor that tends to show up in rents and prices for apartments, hotels and retail space along the Ton Duc Thang – Nguyen Hue – Ba Son corridor.

Update, 22 October 2026: The Bridge Has Closed Its Arch — Opening Targeted for Tet 2027

On the afternoon of 21 October 2026 the pedestrian bridge across the Saigon River completed arch closure. Work began at around 5 am; at about 1 pm the 187-metre, 1,400-tonne steel arch span was fully connected to piers TC1 and TC2, roughly eight hours in. After 4 pm the struts of the 2,000-tonne support frame were lowered off the span, and at about 6:30 pm the barge and frame began pulling out, clearing the site that evening. River traffic past the site was suspended from 2 am to 6 pm on 21 and 22 October.

What is left: surveying the arch geometry and checking cable tension, joint quality and load behaviour, then the deck, railings, architectural lighting, landscaping, escalators and lifts. Nutifood, which is funding the roughly VND 1 trillion project, says the bridge is expected to open around Tet (Lunar New Year) 2027. That is the sponsor’s target; no formal opening date has been announced.

Realtique’s reading: for people living in or buying in central Thu Thiem, the hardest engineering step is done and what remains is mostly finishing work. The next date to watch is the official opening.

Sources: VnExpress 21/10/2026 · Tien Phong via CafeF 22/10/2026.

When Will the Saigon River Pedestrian Bridge Open? The Timeline

The arch closed on the afternoon of 21 October 2026. The next milestone is opening around Tet 2027, according to sponsor Nutifood — no specific date yet. Published milestones so far:

DateMilestoneStatus
29 Mar 2025Groundbreaking at Bach Dang Wharf parkDone
11 May 2026First concrete pour for main pier cap TC2Done
12 Oct 2026Load test of the 3,400-tonne assembly; project about 90% completeDone
2:15 am, 16 Oct 2026Arch loaded onto the barge at Dong Xuyen portDone
Before 21 Oct 2026Barge towed to the Saigon RiverDone
21 Oct 2026Arch closure: 187 m, 1,400 t span joined to both piers (~1 pm); barge and 2,000 t frame removed (evening)Done
After closureStructural checks; deck, railings, lighting, escalators, liftsOpening targeted around Tet 2027 (per Nutifood)

In May 2026 the press reported a target of completing the bridge in September, around National Day on 2 September. That has slipped: the arch closed on 21 October 2026 and Nutifood now targets opening around Tet 2027. We will update this page when a formal opening date is announced.

Load-out of the 3,400-tonne arch at Dong Xuyen port, night of 15–16 Oct 2026 — Photo: chinhphu.vn/LT (Vietnam Government News)

Where Does the Bridge Land, and How Long Is It?

The bridge links Bach Dang Wharf park (Saigon ward, former District 1) with the central square and riverside park of Thu Thiem new urban area (An Khanh ward); on the Thu Thiem side it lands near the junction of Nguyen Thien Thanh and N14 streets. Key figures from published project information:

ItemFigure
Total lengthabout 720 m
Main span187 m steel arch, shaped after a water-coconut leaf
Deck width6–11 m
Navigation clearance80 m wide, 10 m high
Extrasspiral stairs, stairs, lifts, water feature, pump station
Fundingnearly VND 1,000 billion, privately funded by Nutifood

Contractors include Construction Corporation No. 1 (CC1, approaches), Dat Phuong Group (main piers and abutments) and Dai Dung (arch fabrication and assembly).

Graphic: Realtique · Data: project information published by Dan Viet (12 May 2026) and Vietnam Government News (Oct 2026)

The 124 km Journey of the 3,400-Tonne Arch Assembly

The arch was assembled whole at a yard in Dong Xuyen port (Rach Dua ward, formerly Vung Tau) and is travelling to Ho Chi Minh City by water:

  • Load test (12 Oct): about 30 self-propelled modular transporters (SPMTs) lifted the assembly 40 cm for 24 hours to check deflection and stiffness — results met design values.
  • Load-out (night of 15–16 Oct): the 156 m long, 20 m+ high assembly (about 1,400 t of bridge plus 2,000 t of frame) rolled onto a 14,000-tonne barge and was set on 50 supports; done at 2:15 am on 16 Oct.
  • Tow: about 124 km via Ganh Rai Bay and the Dinh, Thi Vai, Long Tau and Nha Be rivers into the Saigon River, moving in daylight only.
  • River closures on the Saigon River on 19 October and from 2 am to 6 pm on 21 and 22 October (HCMC Department of Construction notice, as reported).

The arch, inspired by the water-coconut leaf, at the Dong Xuyen yard before load testing on 12 Oct 2026 — Photo: chinhphu.vn/LT (Vietnam Government News)

What Changes for Thu Thiem?

Today, getting from central District 1 to Thu Thiem means the Saigon River tunnel or the Thu Thiem and Thu Thiem 2 bridges — a car or motorbike trip. The footbridge adds a direct walking route from Bach Dang Wharf to central Thu Thiem. For the apartment market, three things are worth watching:

  • District 1 feels closer for residents and tenants in towers near the Thu Thiem riverfront — buyers who usually weigh Thu Thiem against District 1 and Thao Dien.
  • Another public landmark for central Thu Thiem, home to projects such as The Metropole Thu Thiem and Empire City and to the planned central station (see TOD and the Thu Thiem mega station).
  • Foot traffic and visitors could lift demand for retail space and serviced apartments around the Thu Thiem landing.

We are not putting a price figure on this: the bridge is not open, there is no before-and-after transaction data, and the benefit depends on each tower’s distance to the landing. When viewing a unit, walk the actual route from the lobby to the bridge.

Buying in Thu Thiem as a Foreigner: Three Checks

Better infrastructure makes Thu Thiem more attractive, but the rules for foreign buyers do not change:

  1. The project must be open to foreigners and the tower must still have room under the 30% per-building quota — get it confirmed in writing before paying a deposit (see the 30% quota explained).
  2. The quota ledger must be clean: in October 2026 The Metropole’s developer was fined for late reporting of 272 foreign sales (details).
  3. Ownership term for foreign individuals is up to 50 years, renewable; overseas Vietnamese who keep Vietnamese nationality buy as citizens.

For the wider district, see our Thu Thiem foreign buyer’s guide.

Frequently Asked Questions

What are the two new Bach Dang footbridges, and how do they differ from the Thu Thiem bridge?
They are separate projects. The Thu Thiem bridge is a 720 m pedestrian crossing over the Saigon River, funded at close to VND 1,000 billion, which closed its arch on 21 October 2026 and is targeted to open around Tet 2027. The two new footbridges cross Ton Duc Thang Street on the District 1 side: one at the Nguyen Hue – Ton Duc Thang junction in front of the Majestic Saigon Hotel, the other at Thai Van Lung – Ton Duc Thang in front of The Landmark. Each is a 6 m wide steel structure with lifts. The package is worth more than VND 88 billion under a build–transfer contract requiring no payment from the city, with Great Wealth Trading and Services Co., Ltd. as investor. The draft contract is still being circulated; construction is put at about two months after site handover, and no completion date has been announced.

When will the Saigon River pedestrian bridge open?
The arch closed on the afternoon of 21 October 2026. Deck, railings, lighting and lifts follow; Nutifood expects the bridge to open around Tet 2027, with no formal date announced yet. An earlier target of around 2 September 2026 has slipped.

Where does the Saigon River pedestrian bridge start and end?
It runs from Bach Dang Wharf park (Saigon ward, former District 1) to the central square and riverside park of Thu Thiem new urban area (An Khanh ward), landing near Nguyen Thien Thanh and N14 streets.

How long is the bridge and who paid for it?
About 720 m in total, with a 187 m steel arch main span shaped like a water-coconut leaf and a 6–11 m deck. It cost nearly VND 1,000 billion and is privately funded by Nutifood.

Will the pedestrian bridge raise apartment prices in Thu Thiem?
There is no data yet: the bridge is not open and the effect depends on each tower’s distance to the landing. The clearest change is a direct walking link to former District 1 for residents and tenants in central Thu Thiem.

Can foreigners buy apartments near the bridge in Thu Thiem?
Yes, if the project is on the list open to foreigners and the tower has room under the 30% quota. Foreign individuals can own for up to 50 years, renewable. Get the remaining quota confirmed in writing before paying a deposit.

⚠️ Note: Arch closure on 21 October 2026 has taken place (VnExpress, Tien Phong, 21–22 October). Opening around Tet 2027 is the sponsor’s plan and may change; no formal opening date has been announced. Length and width come from project information published in May 2026. Market effects are Realtique’s assessment, not a price forecast. This is not investment advice.

Realtique Advisory

Considering an apartment in Thu Thiem?

Send Realtique the project and tower you have in mind. We map the real walk to the footbridge and metro, confirm the foreign quota left, and benchmark prices against District 1 and Thao Dien so you can decide on evidence.

📞 Hotline: +84 866 810 689

Grace Le - Realtique
Your advisor

Grace Le

Senior Property Advisor · Realtique

Grace Le helps expatriate buyers and tenants compare Thu Thiem with District 1 and Thao Dien — measuring real walking routes to new links, confirming foreign quota tower by tower, and staying with clients until the certificate is in their name.

Compare Listings