An Phu Interchange Progress (October 2026): What’s Open, What’s Left and the New 2027 Finish Date
Short answer: the An Phu interchange (Binh Trung ward, former Thu Duc) is not finished. As of October 2026 it is about 75–80% complete: tunnels HC1-01 and HC1-02 and flyover ramps N2, N3 and N4 are open; ramp N1.1 is preparing its final span; ramp N1.2 and the widening of Luong Dinh Cua street depend on land — and that is exactly what has just moved. Full completion has slipped from late 2025 to 2027 (the July 2026 plan says Q3 2027).
🔄 Update, 2 November 2026: the compensation deadlock over the 22,000 m² strip along Luong Dinh Cua — stuck for more than two decades — has been broken. As of 1 November 2026, 60 of 67 cases have accepted compensation and more than 12,933 m² has been handed over; the city now states it intends to finish the interchange by 30 April 2027, earlier than the Q3 2027 plan. Details in the “22,000 m²” section below (Tuoi Tre, 1–2 November 2026).
Realtique’s reading of site photos from Cau Duong Viet Nam (16 October 2026) and reports by VTV, Tuoi Tre and Dan Tri: what is open, what is left, why the date keeps moving, and what the interchange means for apartment buyers along Mai Chi Tho, in Thu Thiem and in An Phu.
An Phu Interchange — As of 2 November 2026
Table of Contents
An Phu Interchange in October 2026: What’s Open, What’s Left
Drone photos posted by Cau Duong Viet Nam on 16 October 2026 show crews ready to pave the tunnel roof to reroute traffic and preparing the final span of ramp N1.1. Cross-checked with VTV (6 October) and earlier reports, the status of each element is:
| Element | Function | Status |
|---|---|---|
| Tunnel HC1-01 | Mai Chi Tho to the HCMC – Long Thanh – Dau Giay expressway | Open |
| Tunnel HC1-02 | 480 m, 4 lanes; Ba Dat bridge – Mai Chi Tho – expressway approach | Opened 2 Feb 2026 |
| Ramp N2 | Expressway right turn into Mai Chi Tho | Open |
| Ramp N3 | Mai Chi Tho left turn into Dong Van Cong | Open |
| Ramp N4 | Dong Van Cong to Mai Chi Tho | Open |
| Ramp N1.1 | Mai Chi Tho (from Vo Nguyen Giap) left turn onto the expressway | Final span being prepared; early-October target missed |
| Ramp N1.2 | Link on the Luong Dinh Cua side | Land being handed over since 1 Nov 2026; planned April 2027 |
| Luong Dinh Cua widening | ~600 m inside the An Phu urban-area boundary (whole route 2.3 km, widened from 30 m to 6 lanes per the 2014 approval) | Receiving land; targeted for 30 Apr 2027 |
The city has ordered the remaining land handed over by 30 November 2026, with about VND 1,865 billion budgeted to compensate and resettle 66 households and one organisation (VTV, October 2026) — as of 1 November 2026 that process had reached 60 of 67 cases; see the section below. The Department of Construction put progress at about 75% in September 2026; VTV reports 75–80%.
Tunnel and the Mai Chi Tho – Dong Van Cong junction, October 2026 — Photo: Cau Duong Viet Nam
When Will the An Phu Interchange Be Finished? Four Deadlines So Far
The completion date has been reset at least three times, and a fourth — the first one pointing earlier — was stated in early November 2026:
- Decision of 28 March 2022: 2021–2025.
- January 2026 revision: extended to Q2 2026 (Dan Tri, 28 January 2026).
- Plan reported July 2026: completion in Q3 2027; N1.2 around April 2027; landscaping, cameras and signage by November 2027 (Tuoi Tre). VTV in October simply says 2027.
- Stated 1 November 2026: after the 22,000 m² land deadlock was cleared, the city stated it intends to finish the An Phu interchange by 30 April 2027 (Tuoi Tre). This is earlier than Q3 2027, but it is a stated intention, not a formal decision revising the project timeline.
Counting from groundbreaking in late 2022, the build has stretched from about 36 to 57 months (Realtique’s calculation). Land clearance on the Luong Dinh Cua side is the main cause cited; ramp N1.1 has also missed 30 June and early October 2026. The 2027 date is still a plan and depends on land being handed over by 30 November — and that condition is now being met: 60 of 67 cases had agreed as of 1 November 2026, with 7 left, held up by internal disputes, inheritance paperwork or disagreement over compensation policy.
Clearing the 22,000 m² Deadlock on Luong Dinh Cua: What Was Unlocked, and How Much Has Been Handed Over
The 22,012 m² strip along Luong Dinh Cua is the root reason ramp N1.2 and the street widening stalled — and it had been frozen for more than two decades. In 2001 the Prime Minister allocated 87 ha to the HCMC Urban Development Service Company (today Thu Thiem Real Estate JSC) for the An Phu urban development project, including the 22,012 m² reserved to widen the Luong Dinh Cua right-of-way and build the interchange. In 2014 the Department of Transport approved upgrading Luong Dinh Cua over 2.3 km, widened from 30 m to six lanes; the stretch inside the An Phu project boundary runs about 600 m from Nguyen Hoang street out to the interchange. Work began in 2015 and was suspended from late 2020 for lack of land. The blockage was not technical: it was an unresolved question of which party carried the responsibility and the funding for compensation.
Three moves unlocked it:
- Applying the land-law implementation relief under National Assembly Resolution 254/2025/QH15.
- Amending the Prime Minister’s land-allocation decision to carve the 22,000 m² out of the area assigned to the company and make Binh Trung ward responsible for site clearance — moving the job from a developer to the local authority.
- Re-allocating capital for the Luong Dinh Cua upgrade, including compensation, support and resettlement for the 22,000 m², advanced from the city budget, with Thu Thiem Real Estate JSC obliged to repay it.
Where it stands on 1 November 2026 (figures from Mr Nghiem Duy Binh, director of the Binh Trung ward construction investment project management unit):
| Measure | As of 1 November 2026 |
|---|---|
| Total area to be recovered | More than 22,000 m² (Tran Nao – Nguyen Thi Dinh section), 67 cases affected |
| Accepted compensation | 60 of 67 cases (54 at the time of the count, plus 6 more households persuaded since) |
| Area handed over | More than 12,933 m² — 10 sites handed over, 44 being demolished |
| Paid out or placed in deposit accounts | More than VND 977 billion for 48 of 67 cases |
| Remaining | 7 cases: internal disputes, inheritance paperwork, or disagreement over compensation policy |
Two notes on the numbers, cross-checked by Realtique: (1) the 1 November report gives compensation, support and resettlement capital for the 22,000 m² as “more than 1,662 thousand billion dong”; set against the VND 977 billion already paid for 48 of 67 cases, the correct unit must be billion (just over VND 1,662 billion), not thousand-billion — that reading is Realtique’s, the source does not clarify it. (2) That figure differs from the roughly VND 1,865 billion VTV reported in October 2026 for 66 households and one organisation; the two come from separate announcements, so this article keeps both with their dates rather than merging them. (3) The table above previously described the widening as “about 500 m to 4 lanes” from an earlier source; the 2014 approval specifies 2.3 km, from 30 m to six lanes, with about 600 m inside the An Phu boundary — the table now follows the approval, and this note records the change.
What it means: for over a year, every answer to “when will the An Phu interchange be finished” came down to one variable — land on Luong Dinh Cua. That variable has just moved from unknown to under way, 7 cases left. The interchange is where three major corridors meet — the HCMC – Long Thanh – Dau Giay expressway, Mai Chi Tho boulevard and Luong Dinh Cua — linking the eastern gateway to Long Thanh airport, the Cat Lai port cluster and Thu Thiem and the old city centre. Of everything still outstanding, this is the link with the widest reach.
Source: Tuoi Tre, 1–2 November 2026 (reporters Ai Nhan and Huu Duy; figures attributed to Mr Nghiem Duy Binh).
Graphic: Realtique · Data: project decision of 28 Mar 2022, Jan 2026 revision (Dan Tri), Jul 2026 plan (Tuoi Tre); month counts by Realtique
Scale and Role: The Eastern Gateway With 20,000+ Container Trips a Day
The An Phu interchange is a three-level junction linking Mai Chi Tho Avenue, Luong Dinh Cua and Dong Van Cong streets and the HCMC – Long Thanh – Dau Giay expressway, budgeted at about VND 3,408 billion from the state budget and run by the city’s transport project management board. More than 20,000 container trips pass through daily on the way to Cat Lai port (VTV).
At the outset the developer expected the project to cut congestion by up to 80% (Dan Tri, 2 February 2026). Today, peak hours still jam because ramps N1.1 and N1.2 are unfinished and work zones still occupy the road.
Ramp N1.1 (centre, under scaffolding) looking toward Mai Chi Tho, October 2026 — Photo: Cau Duong Viet Nam
Why It Matters for Long Thanh Airport and the Metro
Long Thanh International Airport is scheduled to start commercial operations of phase 1 in late 2026 (see Long Thanh airport city), and the HCMC – Long Thanh – Dau Giay expressway is being widened. An Phu is where traffic from central HCMC and Thu Thiem joins that expressway — Tuoi Tre warned in July 2026 that an unfinished interchange would become the bottleneck on the airport route.
The planned Thu Thiem – Long Thanh metro line also passes through the area, so 2027 could bring overlapping work zones (overview: five HCMC metro lines breaking ground in late 2026).
What the An Phu Interchange Means for East-Side Apartments
Three areas sit right next to the interchange:
- The Mai Chi Tho corridor: projects such as Eaton Park (Gamuda Land) are on this avenue — once N1.1 and N1.2 open, the drive to the expressway and Long Thanh airport gets shorter, with fewer signals.
- An Phu – Thao Dien: home to many expatriates; separating port and expressway traffic should ease Luong Dinh Cua and Dong Van Cong.
- Thu Thiem: better expressway access via Mai Chi Tho, complementing the Saigon River pedestrian bridge on the District 1 side.
We are not putting a price figure on this: the project is not finished and the benefit varies tower by tower. What you can test is peak-hour travel time — drive from the project you are considering to the expressway at rush hour before deciding.
Buying in East HCMC as a Foreigner: Quick Notes
The Mai Chi Tho – An Phu – Thu Thiem corridor has many projects open to foreigners, but the 30% per-building quota and the 50-year renewable term still apply. Get the project’s listing status and the tower’s remaining quota confirmed in writing before paying a deposit — see the 30% quota explained.
Frequently Asked Questions
Has the 22,000 m² land deadlock on Luong Dinh Cua been cleared?
Yes in mechanism, and handover is under way on the ground. The city applied Resolution 254/2025/QH15, amended the Prime Minister’s land-allocation decision to carve out the 22,000 m² and assign clearance to Binh Trung ward, and re-allocated compensation capital advanced from the city budget (repayable by Thu Thiem Real Estate JSC). As of 1 November 2026, 60 of 67 cases had agreed, more than 12,933 m² was handed over and over VND 977 billion had been paid for 48 of 67 cases; 7 cases remain, held up by internal disputes, inheritance paperwork or disagreement over policy.
When will the An Phu interchange be finished?
Under the plan reported in July 2026, the whole project completes in Q3 2027; VTV in October 2026 said 2027. The original target was 2025 and has been moved at least twice, mainly because of land clearance.
Which parts of the An Phu interchange are open?
Tunnels HC1-01 and HC1-02 (HC1-02 opened on 2 February 2026) and ramps N2, N3 and N4 are in use. Ramp N1.1 is preparing its final span; N1.2 and the Luong Dinh Cua widening have been receiving land since 1 November 2026.
When will ramp N1.1 open?
Earlier targets of 30 June and early October 2026 were both missed. On 16 October 2026 crews were preparing the final span; no new opening date has been announced.
How much does the An Phu interchange cost?
About VND 3,408 billion from the HCMC budget, with groundbreaking in late 2022; compensation and resettlement planned for late 2026 add about VND 1,865 billion for 66 households and one organisation.
Will the An Phu interchange raise apartment prices in east HCMC?
There is not enough data to quantify it. The clearest effect is better access from Mai Chi Tho, An Phu and Thu Thiem to the expressway and Long Thanh airport once N1.1 and N1.2 open; the benefit varies by project location.
⚠️ Note: Element status is compiled from Cau Duong Viet Nam site photos (16 October 2026) and press reports (VTV 6 October, Tuoi Tre July 2026, Dan Tri January–February 2026). Dates for 2026–2027 are plans that have moved before and may move again. Month counts are Realtique’s calculation. Market effects are our assessment, not a price forecast; this is not investment advice.
Looking at apartments along Mai Chi Tho, in An Phu or Thu Thiem?
Send Realtique the project you are considering. We check real infrastructure progress (interchanges, metro, bridges), time the peak-hour drive and confirm the foreign quota, so you decide on evidence.
📞 Hotline: +84 866 810 689

KC Pham
KC Pham advises foreign buyers and overseas Vietnamese on apartments in east Ho Chi Minh City — Thu Thiem, An Phu and the Mai Chi Tho corridor — judging locations by real infrastructure progress rather than renderings.